Industrial Engineering and Production Management In time study, the rating factor is applied to determine Normal time of a worker Standard time of a job Fixation of incentive rate Merit rating of the worker Normal time of a worker Standard time of a job Fixation of incentive rate Merit rating of the worker ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Halsey 50-50 plan, wages for the job will be TR + (S - T) × R TR + [(S - T)/S] × R TR TR + [(S - T)/2] × R TR + (S - T) × R TR + [(S - T)/S] × R TR TR + [(S - T)/2] × R ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time required to complete a job is established and a bonus is paid to the worker based on the exact % of time saved. This type of incentive plan is known as Rowan Plan Halsey Premium Plan Dry work Plan Taylor Plan Rowan Plan Halsey Premium Plan Dry work Plan Taylor Plan ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following layouts is suited to job production? Fixed position layout Product layout Plant layout Process layout Fixed position layout Product layout Plant layout Process layout ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The objective of time study is to determine the time required to complete a job by Slow worker Fast worker New entrant Average worker Slow worker Fast worker New entrant Average worker ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Critical Path Net Work helps an engineer To concentrate his attention on critical activities To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project To divert the resources from noncritical advanced activities to critical activities All of these To concentrate his attention on critical activities To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project To divert the resources from noncritical advanced activities to critical activities All of these ANSWER DOWNLOAD EXAMIANS APP