Industrial Engineering and Production Management
Pick up the incorrect statement from the following. A critical ratio scheduling

Adjusts automatically changes in activity progress
All of the these
Determines the status of each activity
Establishes the relative priorities among various activities on a common basis

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Slack represents the difference between the

Proposed allowable time and the earliest expected time
Latest allowable time and the normal expected time
Normal allowable time and the latest expected time
Latest allowable time and the earliest expected time

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
A big advantage of PERT over Gantt charts is that in the former case

Early start and late finish of an activity are clearly marked
Interrelationship among activities is clearly shown
Activity times are clear
Activities and events are clearly shown

ANSWER DOWNLOAD EXAMIANS APP