Construction Planning and Management Frequency distribution curves If not symmetrical, are called skew curves Having a single lump, are called uninodal curves If symmetrical, are called normal curves All listed here If not symmetrical, are called skew curves Having a single lump, are called uninodal curves If symmetrical, are called normal curves All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The part of a derrick crane include(i) Mast(ii) Boom(iii) Bull wheel(iv) Jackwhich of these statements are correct? (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Crash project duration is obtained by summing the Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities Crash durations for all activities Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities Normal durations for all the activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel. (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i) and (iv) are correct (i), (iii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iv) are correct (i) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be to + 4tm+ tp/5 to + 4tm+ tp/4 to + 4tm+ tp/6 to + 3tm+ tp/3 to + 4tm+ tp/5 to + 4tm+ tp/4 to + 4tm+ tp/6 to + 3tm+ tp/3 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later Performed at slower rate in 15 days Completed 5 days later All listed here Started 5 days later ANSWER DOWNLOAD EXAMIANS APP