Airport Engineering Effective length of a runway is the distance between Point of intersection of the obstruction clearance line and the extended plane of the runway surface, and the other end of the runway Ends of the runway Ends of the clear way on either side Point of intersection of the glide path and the extended plane of the runway surface and the other end of the runway Point of intersection of the obstruction clearance line and the extended plane of the runway surface, and the other end of the runway Ends of the runway Ends of the clear way on either side Point of intersection of the glide path and the extended plane of the runway surface and the other end of the runway ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering The runway orientation is made so that landing and takeoff are None of these Along the wind direction Against the wind direction Perpendicular to wind direction None of these Along the wind direction Against the wind direction Perpendicular to wind direction ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering Zero fuel weight of an aircraft is: Equal to sum of empty operating weight and the maximum pay load Equal to empty operating weight Less than empty operating weight Equal to maximum landing weight Equal to sum of empty operating weight and the maximum pay load Equal to empty operating weight Less than empty operating weight Equal to maximum landing weight ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering As per ICAO, the minimum basic runway length for A and E type of airport will be 1500 m and 600 m 1500 m and 750 m 2100 m and 750 m 2100 m and 600 m 1500 m and 600 m 1500 m and 750 m 2100 m and 750 m 2100 m and 600 m ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering If the monthly mean of average daily temperature for the hottest month of the year is 25°C and the monthly mean of the maximum daily temperature of the same month of the year is 46°C, the airport reference temperature is 35.5°C 32°C 48°C 25°C 35.5°C 32°C 48°C 25°C ANSWER DOWNLOAD EXAMIANS APP
Airport Engineering Which of the following is an example of failure in flexible pavements? Alligator cracking Warping cracks Shrinkage cracks Mud pumping Alligator cracking Warping cracks Shrinkage cracks Mud pumping ANSWER DOWNLOAD EXAMIANS APP