Construction Planning and Management While scheduling a project by C.P.M. All listed here Required time for each activity is established Net work is drawn by connecting the activities and the events A project is divided into various activities All listed here Required time for each activity is established Net work is drawn by connecting the activities and the events A project is divided into various activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Final technical authority of a project lies with Chief Engineer Superintending Engineer Assistant Engineer Executive Engineer Chief Engineer Superintending Engineer Assistant Engineer Executive Engineer ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The technique for establishing and maintaining priorities among the various jobs of a project, is known Short interval scheduling Slotting technique for scheduling Event flow scheduling technique Critical ratio scheduling Short interval scheduling Slotting technique for scheduling Event flow scheduling technique Critical ratio scheduling ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later All listed here Performed at slower rate in 15 days Completed 5 days later Started 5 days later ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 25 20 15 35 25 20 15 35 ANSWER DOWNLOAD EXAMIANS APP