Construction Planning and Management While scheduling a project by C.P.M. A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events A project is divided into various activities Required time for each activity is established All listed here Net work is drawn by connecting the activities and the events ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 35 20 15 25 35 20 15 25 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 2, 3, 4, 5 1, 3, 4, 2, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle? Asphalt Concrete Firm earth Loose sand Asphalt Concrete Firm earth Loose sand ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following statements for a power shovel:(i) Output can be increased by reducing the angle of swing for a given depth of cut.(ii) For a given angle of swing, output will be maximum at optimum depth of cut.(iii) Output can be increased by keeping the depth of cut less than optimum depth.(iv) Output can be increased by increasing the size of shovel. (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (iii) and (iv) are correct (i) and (iv) are correct (i), (ii) and (iv) are correct ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The constraints in case of resource smoothening operation would be Project duration time Both resources and project duration time None of these Resources Project duration time Both resources and project duration time None of these Resources ANSWER DOWNLOAD EXAMIANS APP