Construction Planning and Management
A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be

27 minutes
15 minutes
20.143 minutes
21 minutes

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?

No, because of savings in site labour
No, because of repetitive manufacture of a number of elements
Yes, because of heavier overheads and handling cost
Yes, because of the very high order of quality control for the factory made components