Building Construction
Which one of the following activities is not correct as applicable to brick corbels

Stretcher bond is generally used for the construction of brick corbel
The discontinuous corbels are used to carry heavy concentrated loads
The maximum projection of each corbel course should be limited to a quarter brick at a time
The maximum projection of the corbel should not be more than the thickness of the wall

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
For constructing a terrazzo floor, Pick up the incorrect statement from the following:

After final grinding is over, oxalic acid mixed with water is spread over and rubbed hard with soft material
Glass strips are driven into the layer according to the pattern required
A base course is prepared as in cement concrete flooring
A 32 mm thick layer of cement concrete (1 : 2 : 4) is laid on the base course and the surface is made smooth by trowelling

ANSWER DOWNLOAD EXAMIANS APP