Building Construction The process of making the back ground rough, before plastering, is Hacking Dubbing Blistering Peeling Hacking Dubbing Blistering Peeling ANSWER DOWNLOAD EXAMIANS APP
Building Construction Raft foundation are generally preferred to when the area required for individual footing, is more than 25% to total area 40% to total area 30% of total area 50% of total area 25% to total area 40% to total area 30% of total area 50% of total area ANSWER DOWNLOAD EXAMIANS APP
Building Construction The pile provided with one or more bulles in its vertical shaft, is generally known as Under-ream pile Friction pile Bearing pile Sheet pile Under-ream pile Friction pile Bearing pile Sheet pile ANSWER DOWNLOAD EXAMIANS APP
Building Construction The position of a brick when laid on its side 9 cm × 9 cm with its frog in the vertical plane, is called Brick on bed Brick on edge Brick on end Brick held vertically Brick on bed Brick on edge Brick on end Brick held vertically ANSWER DOWNLOAD EXAMIANS APP
Building Construction Two columns 50 cm × 50 cm and 60 cm × 60 cm carry 80 tonnes and 120 tonnes of loads respectively. The centre to centre distance between columns is 5.00 metres. The permissible bearing capacity of the soil is 20 t/m2. If the footing is not to project more than 25 cm beyond the outside of the smaller column, pick up the correct design parameters of the footing from the following: The length of the foundation slab = 7.00 m Distance of C.G. of the loads from the smaller column = 3.00 m Area of footing slab = 11.00 m2 All listed here The length of the foundation slab = 7.00 m Distance of C.G. of the loads from the smaller column = 3.00 m Area of footing slab = 11.00 m2 All listed here ANSWER DOWNLOAD EXAMIANS APP
Building Construction Couple roof is used for spans 3.5 m or less 3.5 m but less than 5 m 6.5 m but less than 8 m 5 m but less than 6.5 m 3.5 m or less 3.5 m but less than 5 m 6.5 m but less than 8 m 5 m but less than 6.5 m ANSWER DOWNLOAD EXAMIANS APP