Which of the following are the guidelines for the construction of a network diagram?

Dangling must be avoided in a network diagram
Each activity is represented by one and only one arrow in the network
Dummy activity consumes no time or resource
All of the these

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
When slack of an activity is negative

It represents that a programme falls behind schedule and additional resources are required to complete the project in time
All of these
It represents a situation where extra resources are available and the completion of project is not delayed
The activity is critical and any delay in its performance will delay the completion of whole project