Building Construction The vertical member running through middle of a shutter frame, is Reveal Post Mullion Style Reveal Post Mullion Style ANSWER DOWNLOAD EXAMIANS APP
Building Construction The under surface of an arch, is called Intrados Soffit Haunch Back Intrados Soffit Haunch Back ANSWER DOWNLOAD EXAMIANS APP
Building Construction The process of keeping concrete moist for a certain period after its finishing, is known as Curing of concrete Placing of concrete Finishing of concrete Compaction of concrete Curing of concrete Placing of concrete Finishing of concrete Compaction of concrete ANSWER DOWNLOAD EXAMIANS APP
Building Construction In verandah (corridor) floors outward slope is 1 in 50 1 in 60 1 in 70 1 in 40 1 in 50 1 in 60 1 in 70 1 in 40 ANSWER DOWNLOAD EXAMIANS APP
Building Construction The method of moving each brick through a small horizontal distance before it is finally laid in any brick wall and pressing it by means of brick hammer, is known as Placing Troweling Grouting Laying Placing Troweling Grouting Laying ANSWER DOWNLOAD EXAMIANS APP
Building Construction In jack arch floor, the rise is kept 1/8th of the span 1/10th of the span 1/12th of the span 1/6th of the span 1/8th of the span 1/10th of the span 1/12th of the span 1/6th of the span ANSWER DOWNLOAD EXAMIANS APP