Construction Planning and Management In PERT analysis, the time estimates of activities and probability of their occurrence follow Poisson's distribution curve Normal distribution curve None of these Beta distribution curve Poisson's distribution curve Normal distribution curve None of these Beta distribution curve ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Critical path May be longest May be shortest Is always shortest Is always longest May be longest May be shortest Is always shortest Is always longest ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While filling the tender for any work, the contractor considers Site survey Availability of construction materials All listed here Availability of labour Site survey Availability of construction materials All listed here Availability of labour ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management PERT analysis is based on Most likely time Optimistic time All listed here Pessimistic time Most likely time Optimistic time All listed here Pessimistic time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Latest start of an activity is always less than latest event time of preceding node less than or equal to latest event time of preceding node equal to latest event time of preceding node greater than or equal to latest event time of preceding node less than latest event time of preceding node less than or equal to latest event time of preceding node equal to latest event time of preceding node greater than or equal to latest event time of preceding node ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The direct cost of a project with respect to normal time is Infinite Zero Minimum Maximum Infinite Zero Minimum Maximum ANSWER DOWNLOAD EXAMIANS APP