For each storey (or, story) of a building, the depth of exploration should be

3 meters
4 meters
1 meter
2 meters

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
The pile which supports the load partly by friction and partly by resting on hard stratum, is called

Rough pile
Bearing pile
Friction bearing pile
Friction pile

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
A floor constructed with 3 mm marble chips, is known

Marble floor
Terrazzo floor
Chips floor
Mosaic floor

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
Dampness causes

Bleaching of paints
Crumbling of plaster
Growth of termites
Efflorescence

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
The form Work including the props can be removed from beams, only after

14 days
7 days
3 days
21 days

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
The process of keeping concrete moist for a certain period after its finishing, is known as

Placing of concrete
Finishing of concrete
Curing of concrete
Compaction of concrete

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Building Construction

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑