The form work from the sides of beams can be removed only after

4 days
14 days
1 day
7 days

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
For effective drainage, the finished surface of flat roof should have a minimum slope of

1 in 20
1 to 50
1 in 5
1 in 10

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
Rotary drilling is the fastest method in case of

Clay soils
Sandy soil
All of these
Rocky soils

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
The method of moving each brick through a small horizontal distance before it is finally laid in any brick wall and pressing it by means of brick hammer, is known as

Grouting
Laying
Troweling
Placing

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
Crown is located at

Highest point on the intrados of the arch
Highest point on the extrados of the arch
Skew-back of the arch
None of these

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
The lower half portion between crown and skew back of the arch, is called

Haunch
Springing
Spandril
Soffit

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Building Construction

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑