CONSTRUCTION PLANNING AND MANAGEMENT

Construction Planning and Management
The difference between the time avail-to do a job and the time required to do the job, is known as

Float
Duration
Constraint
Event

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The Overall in-charge of an organization at the site responsible for the execution of the works, is

Assistant Engineer
Executive Engineer
Engineer
Junior Engineer

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

4
3
2
1

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
Various activities of a project, are shown on bar charts by

Vertical lines
Crosses
Horizontal lines
Dots

ANSWER DOWNLOAD EXAMIANS APP

Construction Planning and Management
The main disadvantage of line organization, is

Extraordinary delay in communications
Rigid structure
All listed here
Top level executions over work

ANSWER DOWNLOAD EXAMIANS APP
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • ...
  • 31
  • »

GO TO PAGE

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑