Building Construction Which one of the following piles has a cast iron shoe even after removal of the hollow cylindrical steel casing? Vibro pile Both (A) and (C) of the above Simplex pile Pedestal pile Vibro pile Both (A) and (C) of the above Simplex pile Pedestal pile ANSWER DOWNLOAD EXAMIANS APP
Building Construction The single stage well point system of dewatering an excavation can be used if the depth of excavation does not exceed 5 m 10 m 15 m 20 m 5 m 10 m 15 m 20 m ANSWER DOWNLOAD EXAMIANS APP
Building Construction In a colar beam roof There are two horizontal ties, one at the feet and other at the middle of the rafters There is no horizontal tie beam There is a horizontal tie at almost the middle of rafters only There is a horizontal tie at the feet of rafters only There are two horizontal ties, one at the feet and other at the middle of the rafters There is no horizontal tie beam There is a horizontal tie at almost the middle of rafters only There is a horizontal tie at the feet of rafters only ANSWER DOWNLOAD EXAMIANS APP
Building Construction The differential settlement in case of foundations on sandy soils should not exceed 40 mm 65 mm 100 mm 25 mm 40 mm 65 mm 100 mm 25 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction To ensure that supporting area of an offset footing of a boundary wall is fully compressive, the C.G. of load must act Within the middle fifth of the base Within the middle third of the base Neither (A), (B) nor (C) At the centre of the base Within the middle fifth of the base Within the middle third of the base Neither (A), (B) nor (C) At the centre of the base ANSWER DOWNLOAD EXAMIANS APP
Building Construction The ceiling height of a building is Between ceiling and ground level Upto ceiling from the ground level Between ceiling and floor level Upto roof above ground level Between ceiling and ground level Upto ceiling from the ground level Between ceiling and floor level Upto roof above ground level ANSWER DOWNLOAD EXAMIANS APP