Building Construction
Two columns 50 cm × 50 cm and 60 cm × 60 cm carry 80 tonnes and 120 tonnes of loads respectively. The centre to centre distance between columns is 5.00 metres. The permissible bearing capacity of the soil is 20 t/m2. If the footing is not to project more than 25 cm beyond the outside of the smaller column, pick up the correct design parameters of the footing from the following:

Distance of C.G. of the loads from the smaller column = 3.00 m
All listed here
The length of the foundation slab = 7.00 m
Area of footing slab = 11.00 m2

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
Which one of the following activities is not correct as applicable to brick corbels

The maximum projection of each corbel course should be limited to a quarter brick at a time
The maximum projection of the corbel should not be more than the thickness of the wall
Stretcher bond is generally used for the construction of brick corbel
The discontinuous corbels are used to carry heavy concentrated loads

ANSWER DOWNLOAD EXAMIANS APP