Industrial Engineering and Production Management Which one of the following chart gives simultaneously information about the progress of work and machine loading? Man-machine chart Gantt chart Machine load chart Process chart Man-machine chart Gantt chart Machine load chart Process chart ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A big advantage of PERT over Gantt charts is that in the former case Early start and late finish of an activity are clearly marked Activity times are clear Interrelationship among activities is clearly shown Activities and events are clearly shown Early start and late finish of an activity are clearly marked Activity times are clear Interrelationship among activities is clearly shown Activities and events are clearly shown ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management CPM stands for Critical Process Method Combined Process Method Critical Path Method Common Planning Method Critical Process Method Combined Process Method Critical Path Method Common Planning Method ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker Whose output exceeds 67% efficiency On the percentage of standard time On the percentage of time worked On the percentage of time saved Whose output exceeds 67% efficiency On the percentage of standard time On the percentage of time worked On the percentage of time saved ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project All of these It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project All of these It represents a situation where extra resources are available and the completion of project is not delayed ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Bar charts are suitable for Major works All of these Large projects Minor works Major works All of these Large projects Minor works ANSWER DOWNLOAD EXAMIANS APP