Industrial Engineering and Production Management Which of the following equations is not in conformity with others? Ability × motivation = performance Knowledge × skill = ability Attitude × situation = motivation Organization performance × motivation = profits Ability × motivation = performance Knowledge × skill = ability Attitude × situation = motivation Organization performance × motivation = profits ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT has following time estimate Four time estimate One time estimate Two time estimate Three time estimate Four time estimate One time estimate Two time estimate Three time estimate ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Under the Apprenticeship Act All industries employing more than 100 workers have to recruit apprentices Only industries employing more than 500 workers have to recruit apprentices Industries have to train apprentices according to their requirement All industries have to necessarily train the apprentices All industries employing more than 100 workers have to recruit apprentices Only industries employing more than 500 workers have to recruit apprentices Industries have to train apprentices according to their requirement All industries have to necessarily train the apprentices ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The performance of a specific task in CPM is known as Activity Event Contract Dummy Activity Event Contract Dummy ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The assumption in PERT is Activities are fixed and can't be changed Cost of project will always be more than the estimated cost, if no timely corrections are taken A project will always be behind schedule, if left uncorrected A project can be subdivided into a set of predictable, independent activities Activities are fixed and can't be changed Cost of project will always be more than the estimated cost, if no timely corrections are taken A project will always be behind schedule, if left uncorrected A project can be subdivided into a set of predictable, independent activities ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT analysis is based upon Optimistic time Most likely time Pessimistic time All of these Optimistic time Most likely time Pessimistic time All of these ANSWER DOWNLOAD EXAMIANS APP