Power Systems What should be the minimum depth (in metre)of cable trench to dug for laying of 1.1 kV? 1.20. 0.90. 0.75. 1.05. 1.20. 0.90. 0.75. 1.05. ANSWER DOWNLOAD EXAMIANS APP
Power Systems The daily energy produced in thermal power station is 720 MWh at a load factor of 0.6. What is the maximum demand of the station? 30 MW 720 MW 72 MW 50 MW 30 MW 720 MW 72 MW 50 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of following is a medium and low head turbines None of above. Pelton and Kaplan turbines. Francis and Kaplan turbines. Kaplan and Francis turbines. None of above. Pelton and Kaplan turbines. Francis and Kaplan turbines. Kaplan and Francis turbines. ANSWER DOWNLOAD EXAMIANS APP
Power Systems In a 400 kV power network, 360 kV is recorded at 400 kV bus. The reactive power absorbed by a shunt reactor for 50 MVAr, 400 kV connected at the bus is 61.73 MVAr. 45.0 MVAr. 55.56 MVAr. 40.5 MVAr. 61.73 MVAr. 45.0 MVAr. 55.56 MVAr. 40.5 MVAr. ANSWER DOWNLOAD EXAMIANS APP
Power Systems The draw back of NR method as compare to Gauss-Seidel method is/are? large number of iterations both 1 and 2 None of these large requirement of computer memory large number of iterations both 1 and 2 None of these large requirement of computer memory ANSWER DOWNLOAD EXAMIANS APP
Power Systems Alternate formation and breakage of bubbles are called water hamming. All of these surgfication. cavitations. water hamming. All of these surgfication. cavitations. ANSWER DOWNLOAD EXAMIANS APP