Power Systems The draw back of NR method as compare to Gauss-Seidel method is/are? large requirement of computer memory None of these large number of iterations both 1 and 2 large requirement of computer memory None of these large number of iterations both 1 and 2 ANSWER DOWNLOAD EXAMIANS APP
Power Systems Under excited Synchronous phase modifier works as series capacitor shunt reactor any of the above shunt capacitor series capacitor shunt reactor any of the above shunt capacitor ANSWER DOWNLOAD EXAMIANS APP
Power Systems In thermal power plants the size of coal after crushing 20 - 25 mm. 40 mm. 300 mm. 200 - 205 mm. 20 - 25 mm. 40 mm. 300 mm. 200 - 205 mm. ANSWER DOWNLOAD EXAMIANS APP
Power Systems NTPC (National Thermal Power Cooperation) has its only thermal power generating unit in West Bengal at Bakreshwar. Durgapur. Katwa. Farakka. Bakreshwar. Durgapur. Katwa. Farakka. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Peak load power plants is/are pumped storage plant both 1 and 2 nuclear plants diesel plant pumped storage plant both 1 and 2 nuclear plants diesel plant ANSWER DOWNLOAD EXAMIANS APP
Power Systems Reheat cycle in thermal power plant is used to improve condenser performance. reduce loss of heat. utilize heat of flue gases. increase thermal efficiency. improve condenser performance. reduce loss of heat. utilize heat of flue gases. increase thermal efficiency. ANSWER DOWNLOAD EXAMIANS APP