Irrigation Engineering Tortuosity of a meandering river is always greater than 1 equal to 1 less than 1 less than or equal to 1 greater than 1 equal to 1 less than 1 less than or equal to 1 ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The forces, which are considered for the analysis of an elementary profile of a gravity dam under empty reservoir condition, arei) Water pressureii) Self weightiii) Upliftiv) Pressure due to earthquakeThe correct answer is (i), (ii) and (iv) (i), (ii), (iii) and (iv) Only (ii) (i), (ii) and (iii) (i), (ii) and (iv) (i), (ii), (iii) and (iv) Only (ii) (i), (ii) and (iii) ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering With the increase in the quantity of water supplied, the yield of most crops decreases continuously increases upto a certain limit and then decreases increases continuously increases upto a certain limit and then becomes constant decreases continuously increases upto a certain limit and then decreases increases continuously increases upto a certain limit and then becomes constant ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The most suitable location of a canal head work, is Boulders stage of the river Trough stage of the river Rock stage of the river Delta stage of the river Boulders stage of the river Trough stage of the river Rock stage of the river Delta stage of the river ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering V and R are the regime mean velocity and hydraulic mean depth respectively in meters. Lacey's silt factor f is 5V²/2R 3V²/4R 2V²/5R 2V²/√3 R 5V²/2R 3V²/4R 2V²/5R 2V²/√3 R ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering In gravity canals, F.S.L. is Only a few cm above the ground level Always at the ground level Always below the ground level Generally 4 to 5 metres above the ground level Only a few cm above the ground level Always at the ground level Always below the ground level Generally 4 to 5 metres above the ground level ANSWER DOWNLOAD EXAMIANS APP