Railway Engineering To ensure exact gauge, the gauge tie plates are provided at toe of the switch both (A) and (B) None of these nose of crossing toe of the switch both (A) and (B) None of these nose of crossing ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering The desirable rate of change of cant deficiency in case of Metre Gauge is 55 mm/sec 20 mm/sec 35 mm/sec 65 mm/sec 55 mm/sec 20 mm/sec 35 mm/sec 65 mm/sec ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering If a is the angle of crossing, then the number of crossings āNā according to right angle method is given by Vi cosec(a/2) cot(oc/2) cot(a) Vi cot(cc/2) Vi cosec(a/2) cot(oc/2) cot(a) Vi cot(cc/2) ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering The formation width for a double line Broad Gauge track in cutting (excluding drains) as adopted on Indian Railways is 10.82 m 10.21m 8.84 m 6.10 m 10.82 m 10.21m 8.84 m 6.10 m ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Study the following statements regarding creep. i) Creep is greater on curves than on tangent railway track, ii) Creep in new rails is more than that in old rails, iii) Creep is more on steep gradients than on level track. The correct answer is (i)and(ii) (i), (ii) and (iii) (ii) and (iii) only (i) (i)and(ii) (i), (ii) and (iii) (ii) and (iii) only (i) ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering At points and crossings, the total number of sleepers for 1 in 12 turnouts in Broad Gauge is 73 70 72 71 73 70 72 71 ANSWER DOWNLOAD EXAMIANS APP