Construction Planning and Management Time and progress chart of a construction, is also known as Bar chart Modified Mile stone chart Gantt chart All listed here Bar chart Modified Mile stone chart Gantt chart All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Consider the following operations:1. Drilling2. Blasting3. Mucking4. Placing steel5. Placing concreteThe correct sequence of these operations in tunnel construction is 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 1, 2, 3, 4, 5 1, 2, 4, 3, 5 1, 3, 2, 4, 5 1, 3, 4, 2, 5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The reduction in project time normally results in Decreasing the direct cost and increasing indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost Decreasing the direct cost and increasing indirect cost Decreasing the direct cost and indirect cost both Increasing the direct cost and indirect cost both Increasing the direct cost and decreasing the indirect cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its earliest finish time and earliest start time for its successor activity Its latest start time and earliest start time ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Completion of an activity on CPM network diagram, is generally known All listed here Node Event Connector All listed here Node Event Connector ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing.Reason R: If the angle of swing is decreased, the cycle time will be decreased. Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true Both A and R is true but R is not the correct explanation of A Both A and R is true and R is the correct explanation of A A is true but R is false A is false but R is true Both A and R is true but R is not the correct explanation of A ANSWER DOWNLOAD EXAMIANS APP