Construction Planning and Management Time and progress chart of a construction, is also known as Modified Mile stone chart Gantt chart Bar chart All listed here Modified Mile stone chart Gantt chart Bar chart All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Total float for any activity is defined as the difference between Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity Its latest start time and earliest finish time Its latest start time and earliest start time Its earliest finish time and earliest start time for its successor activity Its latest finish time and earliest start time for its successor activity ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be 0.5 More than 50 % Less than 50 % 1 0.5 More than 50 % Less than 50 % 1 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the correct statement from the following with regards to C.P.M. network analysis of projects The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity All listed here ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is Rs. 6,50,000 Rs. 5,75,000 Rs. 8,50,000 Rs. 4,75,000 Rs. 6,50,000 Rs. 5,75,000 Rs. 8,50,000 Rs. 4,75,000 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Setting of question paper Excavation for foundation All listed here Curing of concrete Setting of question paper Excavation for foundation All listed here Curing of concrete ANSWER DOWNLOAD EXAMIANS APP