Power Systems
The time taken by the turbine to fall to 0 rpm speed from 3000 rpm is called

  stopping time.
  damping time.
  settling time.
  coasting time.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The incremental fuel costs for two generating units G1 and G2 are given by Ic1 = 25 + 0.2 PG1 and Ic2 = 32 + 0.2 PG2, where PG1 and PG2 are real powers generated by the units. The economic allocation for a total load of 250 MW, neglecting transmission loss, is given by

 PG1 = 100 MW and PG2 = 150 MW
 PG1 = 142.5 MW and PG2 = 107.5 MW
 PG1 = 109.75 MW and PG2 = 140.25 MW
 PG1 = 125 MW and PG2 = 125 MW

ANSWER DOWNLOAD EXAMIANS APP