The salient feature of functional organisation is

Strict adherence to specification
All of these
Separation of planning and design part
Each individual maintains functional efficiency

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
A big advantage of PERT over Gantt charts is that in the former case

Interrelationship among activities is clearly shown
Activities and events are clearly shown
Activity times are clear
Early start and late finish of an activity are clearly marked