Power Systems The inertia constant of 100 MVA, 50 Hz, 4 pole generator is 10 MJ/MVA. If the mechanical input to the machine is suddenly raised from 50 MW to 75 MW, the rotor acceleration will be equal to 125 electrical degrees/s² 225 electrical degrees/s² 12.5 electrical degrees/s² 22.5 electrical degrees/s² 125 electrical degrees/s² 225 electrical degrees/s² 12.5 electrical degrees/s² 22.5 electrical degrees/s² ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following plants is/are base load plants run off river both 1 and 2 nuclear pump storage run off river both 1 and 2 nuclear pump storage ANSWER DOWNLOAD EXAMIANS APP
Power Systems In a 400 KV network, 360 KV is recorded at a 400 KV bus. The reactive power absorbed by shunt rated for 50 MVAr, 400 KV connected at the bus is 40.5 MVAr. 45 MVAr. 55.56 MVAr. 61.73 MVAr. 40.5 MVAr. 45 MVAr. 55.56 MVAr. 61.73 MVAr. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Maximum power transfer capability of transmission line can be increased by Using series capacitance All of these Parallel transmission lines Using bundled conductors Using series capacitance All of these Parallel transmission lines Using bundled conductors ANSWER DOWNLOAD EXAMIANS APP
Power Systems A Pelton wheel turbine having a rated speed of 300 rpm is connected to an alternator to produce power at 50 Hz. The number of poles required in the alternator is 8 4 10 20 8 4 10 20 ANSWER DOWNLOAD EXAMIANS APP
Power Systems The load duration curve for a system is 8 hours 30 MW, 16 hours 25 MW and 24 hours 20 MW. The load factor will be 0.44. 0.83. 0.25. 1.3. 0.44. 0.83. 0.25. 1.3. ANSWER DOWNLOAD EXAMIANS APP