GETCO Exam Paper (22-07-2015) The fault occurring in transmission actually are mostly L-L L-L-G L-L-L L-G L-L L-L-G L-L-L L-G ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Which power plant may take several days to start up and shunt down? solar power plant none of these Base load Peak load solar power plant none of these Base load Peak load ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) The recent (as on 22/07/2015) Mahakumbh is held at Alahabad Nasik Ujjain Haridwar Alahabad Nasik Ujjain Haridwar ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) The breaking capacity of a CB is usually expressed interms of MW volts amperes MVA MW volts amperes MVA ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In a given current transformer, If permissible current ratio error rated primary current is 5% the CT is suitable for both measuring and protection measuring purpose protection purpose as power transformer both measuring and protection measuring purpose protection purpose as power transformer ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) For a given transformer volte/turn for primary and secondary winding is same depends on load depends on transformer design different same depends on load depends on transformer design different ANSWER EXPLANATION DOWNLOAD EXAMIANS APP emf = 4.44*f*φ*Temf/T = 4.44*f*φ