Industrial Engineering and Production Management The difference between the time available to do the job and the time required to do the job, is known as Constraint Duration Event Float Constraint Duration Event Float ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Current assets include Manufacturing plant and equipment Common stock held by the firm Manufacturing plant Inventories Manufacturing plant and equipment Common stock held by the firm Manufacturing plant Inventories ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Gantt chart provides information about the Proper utilization of manpower Efficient working of machine Material handling Production schedule Proper utilization of manpower Efficient working of machine Material handling Production schedule ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In PERT analysis, critical path is obtained by joining events having -ve slack Dummy activities Zero slack +ve slack -ve slack Dummy activities Zero slack +ve slack ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT Permits management to foresee quickly the impact of variations from the plan Provides an approach for keeping planning up-to-date Provides a way for management to require that planning be done on a uniform and logical basis All of the listed here Permits management to foresee quickly the impact of variations from the plan Provides an approach for keeping planning up-to-date Provides a way for management to require that planning be done on a uniform and logical basis All of the listed here ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management CPM has following time estimate Two time estimate One time estimate Four time estimate Three time estimate Two time estimate One time estimate Four time estimate Three time estimate ANSWER DOWNLOAD EXAMIANS APP