Industrial Engineering and Production Management
A big advantage of PERT over Gantt charts is that in the former case

Interrelationship among activities is clearly shown
Early start and late finish of an activity are clearly marked
Activity times are clear
Activities and events are clearly shown

ANSWER DOWNLOAD EXAMIANS APP