Industrial Engineering and Production Management
In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:

His individual performance
A standard rating system
A merit rating system
A job evaluation system

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Activity slack or float of any event on a PERT/CPM chart is represented by

Latest start time of the event earliest start time of the event
Latest finish time of event earliest finish time of the event
Anyone of the above
Latest start time of succeeding event earliest finish time of preceding event activity time

ANSWER DOWNLOAD EXAMIANS APP