Waste Water Engineering The asbestos cement pipes are generally laid At an angle of 60° At an angle of 30° Vertically Horizontally At an angle of 60° At an angle of 30° Vertically Horizontally ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The recommended detention period for grit chambers is 1 minute 2 minutes 3 minutes 5 minutes 1 minute 2 minutes 3 minutes 5 minutes ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The detention period for plain sedimentation water tanks, is usually 8 to 16 hours 24 to 36 hours 16 to 24 hours 4 to 8 hours 8 to 16 hours 24 to 36 hours 16 to 24 hours 4 to 8 hours ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The minimum diameter of sewer to be adopted is 25 cm 15 cm 12.5 cm 10 cm 25 cm 15 cm 12.5 cm 10 cm ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering House connections to the laterals is generally made by Cast iron Glazed stonewares P.C.C. R.C.C. Cast iron Glazed stonewares P.C.C. R.C.C. ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering If 2% solution of a sewage sample is incubated for 5 days at 20°C and depletion of oxygen was found to be 5 ppm, B.O.D. of the sewage is None of these 250 ppm 225 ppm 200 ppm None of these 250 ppm 225 ppm 200 ppm ANSWER DOWNLOAD EXAMIANS APP