Building Construction
In a colar beam roof

There is no horizontal tie beam
There is a horizontal tie at almost the middle of rafters only
There are two horizontal ties, one at the feet and other at the middle of the rafters
There is a horizontal tie at the feet of rafters only

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
Which one of the following activities is not correct as applicable to brick corbels

Stretcher bond is generally used for the construction of brick corbel
The discontinuous corbels are used to carry heavy concentrated loads
The maximum projection of each corbel course should be limited to a quarter brick at a time
The maximum projection of the corbel should not be more than the thickness of the wall

ANSWER DOWNLOAD EXAMIANS APP