Performance rating is equal to Observed performance - normal performance None of these Observed performance + normal performance Observed performance × normal performance TRUE ANSWER : ? YOUR ANSWER : ?
PERT analysis is based upon Most likely time Optimistic time All of these Pessimistic time TRUE ANSWER : ? YOUR ANSWER : ?
A dummy activity in a net work diagram Is represented by a dotted line Does not consume time or resources Is an artificial activity All of these TRUE ANSWER : ? YOUR ANSWER : ?
In the Halsey system of wage incentive plan, a worker is Not paid any bonus till his efficiency Ensured of minimum wages Paid as per efficiency Never a loser TRUE ANSWER : ? YOUR ANSWER : ?
'O' on a PERT/CPM chart represents Dangling event An event to be transferred to other network chart A significant event representing some milestone An ordinary event TRUE ANSWER : ? YOUR ANSWER : ?
ABC analysis deals with Ordering schedule of job Flow of material Controlling inventory costs money Analysis of process chart TRUE ANSWER : ? YOUR ANSWER : ?
Critical path on PERT/CPM chart is obtained by joining the events having Maximum slack Minimum slack No slack Average slack TRUE ANSWER : ? YOUR ANSWER : ?
Work study is done with the help of Process chart Stop watch All of the these Material handling TRUE ANSWER : ? YOUR ANSWER : ?
Actual performance of a task is called An activity None of these An event A duration TRUE ANSWER : ? YOUR ANSWER : ?
The chart which gives an estimate about the amount of materials handling between various work stations is known as Operation chart Travel chart Flow chart Process chart TRUE ANSWER : ? YOUR ANSWER : ?