The rate of payment is made for 100 cu m (per % cu m) in case of Excavation in trenches for foundation Rock cutting All of these Earth work in excavation TRUE ANSWER : ? YOUR ANSWER : ?
The plinth area of a building not includes Lift and wall including landing Area of the walls at the floor level Internal shaft for sanitary installations up to 2 sq m. in area Area of cantilevered porch TRUE ANSWER : ? YOUR ANSWER : ?
A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved. 27,500 m³ 26,000 m³ 26,500 m³ 27,000 m³ TRUE ANSWER : ? YOUR ANSWER : ?
The following item of earth work is not measured separately. All listed here Setting out of works Site clearance Steps in deep excavation TRUE ANSWER : ? YOUR ANSWER : ?
While estimating the qualities for the construction of a building, the correct metric unit is Square meters for volume Cubic metre for area Meter for length Liter for capacity TRUE ANSWER : ? YOUR ANSWER : ?
The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is None of these (6 + 15) chains (6 + 12) chains (6 + 18) chains TRUE ANSWER : ? YOUR ANSWER : ?
Pick up the correct statement in case of water supply. All of these Pipes are classified according to their sizes and quality Pipes laid in trenches and pipes fixed to walls are measured separately Cutting through walls and floors are included with the item TRUE ANSWER : ? YOUR ANSWER : ?
The area is measured correct to the nearest 0.03 sqm 0.02 sqm 0.04 sqm 0.01 sqm TRUE ANSWER : ? YOUR ANSWER : ?
Cost of fittings and their fixing is specified for the following sanitary fittings Flushing pipes All listed here Lavatory basins Water closets TRUE ANSWER : ? YOUR ANSWER : ?
In the mid-section formula All of these The volume of the earth work is calculated by multiplying the mid-section area by the distance between the two original sections The mean depth is the average of depths of two consecutive sections The area of mid-sections is calculated by using mean depth TRUE ANSWER : ? YOUR ANSWER : ?