The height of the sink of wash basin above floor level is kept 75 cm to 80 cm 60 cm 70 cm 80 cm TRUE ANSWER : ? YOUR ANSWER : ?
The expected out turn of 12 mm plastering with cement mortar is 2.5 sq m 8.0 sq m 4.0 sq m 6.0 sq m TRUE ANSWER : ? YOUR ANSWER : ?
According to ISI method of measurement, the order of the sequence is None of these Length, breadth, height Height, length, breadth Breadth, length, height TRUE ANSWER : ? YOUR ANSWER : ?
The rate of payment is made for 100 cu m (per % cu m) in case of Earth work in excavation Rock cutting Excavation in trenches for foundation All of these TRUE ANSWER : ? YOUR ANSWER : ?
The inspection pit or chamber is a manhole provided in a base drainage system All of these At every 30 m intervals At every change of direction At every change of gradient TRUE ANSWER : ? YOUR ANSWER : ?
The area of a sloping surface of a protective embankment of mean height‘d’, side slopes S: 1 and length ‘L’ is L.D √(1 + s²) √[d² × (ds)²] d × d × s 2 L.D √(1 + s²) TRUE ANSWER : ? YOUR ANSWER : ?
The expected out turn of cement concrete 1 : 2 : 4 per mason per day is 2.5 m³ 5.0 m³ 1.5 m³ 3.5 m³ TRUE ANSWER : ? YOUR ANSWER : ?
Anti-siphonage pipe is connected to Bottom of P trap W.C. Main soil pipe Side of water closet Top of P trap W.C. TRUE ANSWER : ? YOUR ANSWER : ?
The floor area includes the area of the balcony up to 0.25 0.75 1 0.5 TRUE ANSWER : ? YOUR ANSWER : ?
Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds 0.04 0.02 0.025 0.05 TRUE ANSWER : ? YOUR ANSWER : ?