Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 1 and 4 are correct TRUE ANSWER : ? YOUR ANSWER : ?
The Overall in-charge of an organization at the site responsible for the execution of the works, is Executive Engineer Engineer Junior Engineer Assistant Engineer TRUE ANSWER : ? YOUR ANSWER : ?
The part of a derrick crane include<br/>(i) Mast<br/>(ii) Boom<br/>(iii) Bull wheel<br/>(iv) Jackwhich of these statements are correct? (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct (i), (ii) and (iii) are correct TRUE ANSWER : ? YOUR ANSWER : ?
The independent float affects only None of these The particular activity involved Preceding activities Succeeding activities TRUE ANSWER : ? YOUR ANSWER : ?
Updating may result in All of these Change of critical path Increase of project completion time Decrease of project completion time TRUE ANSWER : ? YOUR ANSWER : ?
The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct? (i), (ii) and (iii) are correct (i), (iii) and (iv) are correct (i), (ii) and (iv) are correct (ii), (iii) and (iv) are correct TRUE ANSWER : ? YOUR ANSWER : ?
A contractor has two options;(l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he should invest in neither of the two projects should invest in project A should invest in project B could invest in either of the two projects TRUE ANSWER : ? YOUR ANSWER : ?
Sensitivity analysis is a study of Comparison of assets and liabilities Change in output due to change in input Economics of cost and benefits of the project Comparison of profit and loss TRUE ANSWER : ? YOUR ANSWER : ?
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is 24 None of these 19 14 TRUE ANSWER : ? YOUR ANSWER : ?