Construction Planning and Management Power stations are generally treated as Light construction Heavy construction Industrial construction Electrical construction Light construction Heavy construction Industrial construction Electrical construction ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management While scheduling a project by C.P.M. Net work is drawn by connecting the activities and the events All listed here Required time for each activity is established A project is divided into various activities Net work is drawn by connecting the activities and the events All listed here Required time for each activity is established A project is divided into various activities ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is 25 20 15 35 25 20 15 35 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The normal time required for the completion of project in the above problem is 13 days 9 days 14 days 19 days 13 days 9 days 14 days 19 days ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management A golden rule for the procurement of construction stones, suggests 33% at the site and 67% under procurement 100% at the site 50% at the site and 50% under procurement 67% at the site and 33% under procurement 33% at the site and 67% under procurement 100% at the site 50% at the site and 50% under procurement 67% at the site and 33% under procurement ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Which one of the following represents an activity? Setting of question paper Curing of concrete Excavation for foundation All listed here Setting of question paper Curing of concrete Excavation for foundation All listed here ANSWER DOWNLOAD EXAMIANS APP