Industrial Engineering and Production Management One of the basic essentials of an incentive plan is that A differential piece rate system should exist All standards should be based on time studies Minimum wages should be guaranteed Provide incentive to group efficiency performance A differential piece rate system should exist All standards should be based on time studies Minimum wages should be guaranteed Provide incentive to group efficiency performance ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Standing orders which are statutory are applicable to All industries employing more than 100 workers All industries Only major industries All process industries and thermal power plants All industries employing more than 100 workers All industries Only major industries All process industries and thermal power plants ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Templates are used for A planning layout Advancing a programme in automatic machines Copying complicated profiles Flow of material A planning layout Advancing a programme in automatic machines Copying complicated profiles Flow of material ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time. Equal to One-fourth Twice One-half Equal to One-fourth Twice One-half ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is positive Any one of the above It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project It represents a situation where extra resources are available and the completion of project is not delayed Any one of the above It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project It represents a situation where extra resources are available and the completion of project is not delayed ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Abbreviated work factor data is applied for Material handling operation Maintenance operation Packing and shipping operation All of these Material handling operation Maintenance operation Packing and shipping operation All of these ANSWER DOWNLOAD EXAMIANS APP