Mho relay is usually employed for protection of

 any line
 medium transmission lines only
 short transmission lines only
 long transmission lines only

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The incremental fuel costs for two generating units G1 and G2 are given by Ic1 = 25 + 0.2 PG1 and Ic2 = 32 + 0.2 PG2, where PG1 and PG2 are real powers generated by the units. The economic allocation for a total load of 250 MW, neglecting transmission loss, is given by

 PG1 = 125 MW and PG2 = 125 MW
 PG1 = 109.75 MW and PG2 = 140.25 MW
 PG1 = 100 MW and PG2 = 150 MW
 PG1 = 142.5 MW and PG2 = 107.5 MW

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Gross head of an hydroelectric power station is

 the height of water level in the river where the tail race is provided.
  the difference of water level between the level in storage and tail race.
 the height of water level in the river where the storage is provided.
 all of above.