Industrial Engineering and Production Management Standing orders which are statutory are applicable to All process industries and thermal power plants Only major industries All industries All industries employing more than 100 workers All process industries and thermal power plants Only major industries All industries All industries employing more than 100 workers ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In the Halsey 50-50 plan, the following are rewarded more Past average workers Past good workers All of the these Past poor workers Past average workers Past good workers All of the these Past poor workers ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Gantt charts are used for Linear programming Scheduling and routing Production schedule Forecasting sales Linear programming Scheduling and routing Production schedule Forecasting sales ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In perpetual inventory control, the material is checked as it reaches its Average value Middle value Minimum value Maximum value Average value Middle value Minimum value Maximum value ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Service time in queuing theory is usually assumed to follow Exponential law Erlang distribution Poisson’s distribution Normal distribution Exponential law Erlang distribution Poisson’s distribution Normal distribution ANSWER DOWNLOAD EXAMIANS APP