Industrial Engineering and Production Management
Pick up the incorrect statement from the following. A critical ratio scheduling

Establishes the relative priorities among various activities on a common basis
Adjusts automatically changes in activity progress
Determines the status of each activity
All of the these

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
When slack of an activity is positive

It represents a situation where extra resources are available and the completion of project is not delayed
It represents that a programme falls behind schedule and additional resources are required to complete the project in time
The activity is critical and any delay in its performance will delay the completion of whole project
Any one of the above