Waste Water Engineering In case of sewer lines Test for straightness is carried out with the help of a lamp and mirror Obstruction test is carried out with the help of smooth ball of diameter 13 mm All listed here Water test is carried out to check water tightness of the joints Test for straightness is carried out with the help of a lamp and mirror Obstruction test is carried out with the help of smooth ball of diameter 13 mm All listed here Water test is carried out to check water tightness of the joints ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The recommended detention period for grit chambers is 3 minutes 1 minute 2 minutes 5 minutes 3 minutes 1 minute 2 minutes 5 minutes ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The algae dies out in the zone of Active decomposition Recovery Cleaner water Degradation Active decomposition Recovery Cleaner water Degradation ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering In very first stage of decomposition of the organic matter in sewage Nitrites are formed Nitrates are formed Ammonia is formed Carbondioxide is formed Nitrites are formed Nitrates are formed Ammonia is formed Carbondioxide is formed ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering In septic tanks, The clear space between the baffle top and covering slab is about 7.5 cm The baffles or tees are extended up to top level of scum Free board of 0.3 m may be provided All listed here The clear space between the baffle top and covering slab is about 7.5 cm The baffles or tees are extended up to top level of scum Free board of 0.3 m may be provided All listed here ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Flocculated particles do not change their Shape Size None of these Weight Shape Size None of these Weight ANSWER DOWNLOAD EXAMIANS APP