Building Construction
In case of Raymond pile

Lengths vary from 6 m to 12 m
All listed here
Diameter of pile at bottom varies from 20 cm to 28 cm
Diameter of top of piles varies from 40 cm to 60 cm

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
Which one of the following activities is not correct as applicable to brick corbels

The maximum projection of each corbel course should be limited to a quarter brick at a time
Stretcher bond is generally used for the construction of brick corbel
The maximum projection of the corbel should not be more than the thickness of the wall
The discontinuous corbels are used to carry heavy concentrated loads

ANSWER DOWNLOAD EXAMIANS APP