Construction Planning and Management If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be More than 50 % Less than 50 % 1 0.5 More than 50 % Less than 50 % 1 0.5 ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? Yes, because of the very high order of quality control for the factory made components No, because of savings in site labour No, because of repetitive manufacture of a number of elements Yes, because of heavier overheads and handling cost Yes, because of the very high order of quality control for the factory made components No, because of savings in site labour No, because of repetitive manufacture of a number of elements Yes, because of heavier overheads and handling cost ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The object of technical planning, is All listed here Preparation of specifications Initiating the procurement action of resources Preparation of estimates All listed here Preparation of specifications Initiating the procurement action of resources Preparation of estimates ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as Free float Dummy Event Constraint Free float Dummy Event Constraint ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management Pick up the PERT event from the following: All listed here Laying of concrete started Digging of foundation started Digging of foundation completed All listed here Laying of concrete started Digging of foundation started Digging of foundation completed ANSWER DOWNLOAD EXAMIANS APP
Construction Planning and Management If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is 1500 cum 1000 cum 500 cum 2000 cum 1500 cum 1000 cum 500 cum 2000 cum ANSWER DOWNLOAD EXAMIANS APP