Docks and Harbor Engineering If H is the height of the wave expected, then the height of the breakwater is generally taken as 1.2 H to 1.25 H above the high water level 1.2 H to 1.25 H above the mean sea level 1.2 H to 1.25 H above the datum 1.2 H to 1.25 H above the low water level 1.2 H to 1.25 H above the high water level 1.2 H to 1.25 H above the mean sea level 1.2 H to 1.25 H above the datum 1.2 H to 1.25 H above the low water level ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering The most popular method of construction of wall breakwaters is Low level method None of these Staging method Barge method Low level method None of these Staging method Barge method ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering Consider the following statements.(i) Fender is the cushion provided on the face of the jetty for ships to come in contact,(ii) Slip is the space of water area between two adjacent piers where ships are berthed,(iii) Pier head is a structure constructed near the tip of a break water near the harbour entrance. Of the statements (i) and (iii) are correct (i) and (ii) are correct (i), (ii) and (iii) are correct (ii) and (iii) are correct (i) and (iii) are correct (i) and (ii) are correct (i), (ii) and (iii) are correct (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering Dead weight tonnage of a ship(i) varies with latitude and season(ii) is more than displacement tonnage(iii) is the difference between displacement load and displacement light of these statements (i) and (ii) are correct Only (iii) is correct (i) and (iii) are correct (ii) and (iii) are correct (i) and (ii) are correct Only (iii) is correct (i) and (iii) are correct (ii) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering Which of the following type of sea walls results in greatest protection of shore structures? sea wall with batter sea wall with concave face vertical sea wall stepped sea wall sea wall with batter sea wall with concave face vertical sea wall stepped sea wall ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering As compared to wall type breakwater, mound type breakwater Requires low maintenance cost Requires skilled labor Results in less damage due to gradual failure Requires less material Requires low maintenance cost Requires skilled labor Results in less damage due to gradual failure Requires less material ANSWER DOWNLOAD EXAMIANS APP