GETCO Exam Paper (30-11-2008) A CB under normal conditions, should be inspected once in a week 5 years 3 or 6 months a month a week 5 years 3 or 6 months a month ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) Isolaters used in transmission lines are capable of breaking charging current fault current no current load current charging current fault current no current load current ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) In the protection scheme relay functions as _____ device switching sensing none of these breaking switching sensing none of these breaking ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) Burden of the relay is _____ rating of relay watt voltage volt-amp. current watt voltage volt-amp. current ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (30-11-2008) In an over current protection, the setting of earth fault relay is _____ the phase fault relay. less than more than equal to not related in less than more than equal to not related in ANSWER DOWNLOAD EXAMIANS APP