Building Construction
For providing a raft foundation, the following activities are involved1.Ramming the foundation bed2.Excavation of the soil upto required depth3.Laying the reinforcement over the foundation bed4.Curing the cement concrete placed over reinforcement5.Pouring the cement concrete over the reinforcementThe correct sequence is

5, 4, 3, 2, 1
2, 1, 3, 5, 4
1, 2, 3, 4, 5
3, 2, 5, 1, 4

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
Pick up the correct statement about silt soil from the following:

In organic fine grained silt soil possesses no plasticity
The least plastic type normally consists of more or less equidimensional grains of quartz
All listed here
The silt soil has particle size from 0.02 mm to 0.06 mm

ANSWER DOWNLOAD EXAMIANS APP