Waste Water Engineering For a grit chamber, if the recommended velocity of flow is 0.2 m/sec and detention period is 2 minutes, the length of the tank, is 20 m 30 m 24 m 16 m 20 m 30 m 24 m 16 m ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering A sewer running partially full and hurried with back filled, fails in compression due to Weight of the back fill Weight of the pipe Superimposed traffic loads All listed here Weight of the back fill Weight of the pipe Superimposed traffic loads All listed here ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The rate of accumulation of sludge per person per year, is 10 litres 25 litres 20 litres 15 litres 10 litres 25 litres 20 litres 15 litres ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The arrangement made for passing the sewer line below an obstruction below the hydraulic gradient lines called Depressed sewer all of these Sag pipe Inverted syphon Depressed sewer all of these Sag pipe Inverted syphon ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering If the length of overland flow from the critical point to the mouth of drain is 13.58 km and difference in level between the critical point and drain mouth is 10 m, the inlet time is 2 hours 4 hours 6 hours 8 hours 2 hours 4 hours 6 hours 8 hours ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Depletion of ozone layer in the outer atmosphere may cause Bronchitis Lung cancer Skin cancer Heart disorder Bronchitis Lung cancer Skin cancer Heart disorder ANSWER DOWNLOAD EXAMIANS APP