Power Systems Find the number of strands of ACSR conductor for 3 layer transmission line? 29 19 7 1 29 19 7 1 ANSWER DOWNLOAD EXAMIANS APP
Power Systems Transmission line has a length of 300 km, operating at sending end voltage Vs = 1 pu, find the receiving end voltage(Vr) at no load? 0.098 pu 0.98 pu 1 pu 1.098 pu 0.098 pu 0.98 pu 1 pu 1.098 pu ANSWER DOWNLOAD EXAMIANS APP
Power Systems A generator has a rating of 10 MVA, 5 kV has a reactance of 0.02 pu. Find the reactance at a new base values of 50 MVA, 10 kV? 0.05 0.25 0.025 0.02 0.05 0.25 0.025 0.02 ANSWER DOWNLOAD EXAMIANS APP
Power Systems Consider a three phase, 50 Hz, 11 kV distribution system. Each of the conductors is suspended by an insulator string having two identical porcelain insulators. The self capacitance of the insulators is 5 times the shunt capacitance between the link and ground. Find the voltage across the two insulators V1 and V2? (V1 = Voltage of disc nearest to the conductor) V1 = 2.89 kV and V2 = 3.46 kV V1 = 5 kV and V2 = 6 kV V1 = 3.46 kV and V2 = 2.89 kV V1 = 6 kV and V2 = 5 kV V1 = 2.89 kV and V2 = 3.46 kV V1 = 5 kV and V2 = 6 kV V1 = 3.46 kV and V2 = 2.89 kV V1 = 6 kV and V2 = 5 kV ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following quantities are to be calculated for generator bus? P and V Q and δ P and Q δ and V P and V Q and δ P and Q δ and V ANSWER DOWNLOAD EXAMIANS APP
Power Systems The load duration curve for a system is 8 hours 30 MW, 16 hours 25 MW and 24 hours 20 MW. The load factor will be 0.83. 0.44. 0.25. 1.3. 0.83. 0.44. 0.25. 1.3. ANSWER DOWNLOAD EXAMIANS APP