Irrigation Engineering Disposal of extra excavated earth of canals, is utilized to provide a spoil bank on Both sides All listed here Left side Right side Both sides All listed here Left side Right side ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering Irrigation canals are generally aligned along Straight line Ridge line Valley line Contour line Straight line Ridge line Valley line Contour line ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The total capacity of a reservoir is 25 million cubic metres and dead storage is 5 million cubic metres. If the average volume of sediment deposition is 0.10 million cubic metre per year, then the usefulness of the reservoir will start reducing after 50 years 250 years 200 years 150 years 50 years 250 years 200 years 150 years ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The peak of a 4 hour flood hydrograph is 240 m3/sec . If the rainfall excess is 80 mm and base flow which is constant is 40 m3/sec, then the peak of 4-hours unit hydrograph will be 20 m3/sec 25 m3/sec 30 m3/sec 35 m3/sec 20 m3/sec 25 m3/sec 30 m3/sec 35 m3/sec ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be 1/(1-0.9°10) 1 – (0.9)°l0 1 + (0.9)010 1/(1+ 0.9010) 1/(1-0.9°10) 1 – (0.9)°l0 1 + (0.9)010 1/(1+ 0.9010) ANSWER DOWNLOAD EXAMIANS APP
Irrigation Engineering The ratio of average values of shear stresses produced on the bed and the banks of a channel due to flowing water is greater than 1 less than 1 equal to 1 equal to zero greater than 1 less than 1 equal to 1 equal to zero ANSWER DOWNLOAD EXAMIANS APP